PMP® Test Questions

 

Answer the questions below to get an idea if you are ready for the PMP® Exam. All questions are aligned to the latest PMI® Standard and are referencing to the latest edition of the PMBOK® Guide.

ID: 10662en
"In a project where the buyer and seller are in different countries, it is generally best to handle currency exchange rate fluctuations by:
"
Negotiating an equitable settlement once the contract is complete
Using the exchange rate in effect on the day invoices are received.
Defining procedures for handling currency rate within the contract
Setting the exchange rate at the start of the contract.

 
"PMP", "CAPM", "PgMP", "PMI" and "PMBOK GUIDE" are registered trademarks of the Project Management Institutes (PMI)
Choose a language